A fiber is specified on a datasheet as 9/125 µm. What does this specification tell the technician?
Show answer & explanation
Correct answer: B - It is single-mode fiber, with a 9 µm core and 125 µm cladding
10 free, exam-style Broadband Fiber Transport Specialist (BFTS) practice questions with answers and explanations. No signup required. Work through them below, then take the full free BFTS practice test to study every exam domain.
A fiber is specified on a datasheet as 9/125 µm. What does this specification tell the technician?
Correct answer: B - It is single-mode fiber, with a 9 µm core and 125 µm cladding
On a long single-mode link operating at a high bit rate, pulses spread out because the different wavelengths emitted by the source travel at slightly different speeds. This effect is called:
Correct answer: D - Chromatic dispersion
An engineer plans to add an erbium-doped fiber amplifier (EDFA) to a wavelength-division link. Which statement about the EDFA is correct?
Correct answer: A - It provides optical gain primarily in the C-band, roughly 1530 to 1565 nm
In a Distributed Access Architecture (DAA) built on Remote PHY, which function is relocated out to the node?
Correct answer: C - The physical (PHY) layer, while the MAC/core remains in the headend
Which approach transports traditional RF cable signals over a fiber plant all the way to an optical unit at the subscriber's home?
Correct answer: B - RFoG (RF over Glass)
A 40 km span uses fiber rated at 0.25 dB/km, has 4 connectors at 0.5 dB each, and 8 fusion splices at 0.1 dB each. What is the total link loss?
Correct answer: C - 12.8 dB
A receiver datasheet lists its sensitivity as -25 dBm. What does the 'm' in dBm signify?
Correct answer: A - An absolute power level referenced to 1 milliwatt
Testing a short patch cord with an OTDR, a technician cannot resolve a connector event located very close to the launch point. What is the MOST likely reason?
Correct answer: D - The connector event falls within the OTDR's dead zone
Which method provides the MOST accurate end-to-end insertion-loss measurement of an installed fiber link?
Correct answer: B - A calibrated light source paired with an optical power meter
Before any underground fiber boring or trenching begins, the FIRST required action is to:
Correct answer: C - Request utility locates so existing lines are marked